Current reports
Current report no. 20/2021
Integrated permit – annulment of the contested decision
Legal basis:
Art. 17 item 1 MAR – inside information
Contents of the report:
Zespół Elektrowni Pątnów-Adamów-Konin SA (the "Company") informs that on July 15, 2021, the Company received information that the Provincial Administrative Court in Warsaw, at a closed session, by a judgment of July 14, 2021, file ref. IV SA / Wa 387/21, revoked the decision of the Minister of Climate and Environment of December 22, 2020, challenged by the Greenpeace Polska Foundation, on the basis of which the decision of the Marshal of the Wielkopolska Province of October 2, 2020, on the adjustment of the integrated permit for the operation of the Fuel Combustion Installation at Pątnów Power Plant and Konin Power Plant to the requirements of BAT conclusions, providing derogations from the emission limit values.
As a result of the above-mentioned judgment, the Decision of the Minister of Climate has no legal effect, and the Provincial Administrative Court in Warsaw has not overruled the decision of the first instance body, i.e. the Marshal's Decision.
As at July 15, 2021, the Company had not received the justification for the above-mentioned judgment. The company is waiting for the preparation and delivery of the justification for the above-mentioned judgment by the Provincial Administrative Court.
Signatures of persons representing the Company:
Maciej Nietopiel – Vice President of the Management Board
Katarzyna Sobierajska – Vice President of the Management Board