Current reports
Current report no. 16/2021
Integrated permit - annulment of the contested decision
Legal basis:
Art. 17 item 1 MAR – inside information
Contents of the report:
With reference to the current report No. 12/2021 of April 9, 2021 Zespół Elektrowni Pątnów-Adamów-Konin SA ("Company") informs that the Company received a copy of the judgment of the Provincial Administrative Court in Warsaw along with the justification in the case from the complaint of the Greenpeace Polska Foundation on the decision of the Minister of Climate of August 4, 2020 on changing the conditions of the integrated permit for the fuel combustion installation at Pątnów II Power Plant.
Pursuant to the above-mentioned judgment, the contested decision was revoked due to the fact that it was issued in breach of procedural law to a degree that could significantly affect the content of the decision. The decision indicates that the Minister of Climate and Environment should re-conduct the proceedings and issue a new decision, taking into account the recommendations contained in the justification of the judgment of the Provincial Administrative Court in Warsaw.
Signatures of persons representing the Company:
Piotr Woźny – President of the Management Board
Maciej Nietopiel – Vice President of the Management Board