ZE PAK S.A. WEBSITE

Current reports

Current reports

Current reports

Current report no. 12/2021

Integrated permit - annulment of the contested decision 

 

Legal basis:

Art. 17 item 1 MAR – inside information

 

Contents of the report:

On April 9, 2021, the Provincial Administrative Court in Warsaw, at a closed session, heard the case from the complaint of the Greenpeace Polska Foundation against the decision to change the terms of the integrated permit for the fuel combustion installation at Pątnów II Power Plant. According to information from the e-listing system of the Provincial Administrative Court in Warsaw, “The contested decision has been repealed. The costs of the proceedings have been reimbursed”. Further information will be provided after the Company has read the judgment.  

                                                                                                                           

 

  

Signatures of persons representing the Company:

Piotr Woźny  – President of the Management Board

Maciej Nietopiel – Vice President of the Management Board

back