Current report no. 3/2019

Decision on Tomisławice open-pit

 

Legal basis:

Art. 17 item 1 MAR – inside information

 

Contents of the report:

With reference to current reports no. 34/2014 and 10/2012 as well as information on court proceedings regarding environmental decision for Tomisławice open-pit contained in subsequent financial reports, Zespół Elektrowni Pątnów-Adamów-Konin SA (the "Company") informs that on 23rd January 2019, the Company received information about the decision issued by the Local Government Appeal Court in Konin refusing to annul the environmental decision issued on August 7, 2007 by the Head of Wierzbinek Commune related to the exploitation of Tomisławice lignite open pit.

 

The case was considered by the Local Government Appeals Court in Konin again, as a result of the decision of the Provincial Administrative Court in Poznań, which after several years of administrative court proceedings finally annulled the previous decision of the Local Government Appeal Court of 25th  March 2009 refusing to annul the environmental decision.

 

The decision of the Local Government Appeal Court in Konin, dated January 18th, 2019, means that the environmental decision issued on August 7, 2007 by the Head of Wierzbinek Commune is still in legal circulation. PAK KWB Konin SA (a subsidiary of the Company) expects to receive the decision with justification. The decision is not final. The parties have the right to submit an application for reconsideration of the case by the Local Government Appeal Court in Konin.

 

 

 

Signatures of persons representing the Company:

Marcin Ginel  – Vice President acting President of the Management Board

Paweł Markowski – Vice President of the Management Board