Conclusion of the contract regarding the dismantling of facilities at Adamów Power Plant

On May 6, 2020 Zespół Elektrowni Pątnów-Adamów-Konin SA concluded a contract with MK Explosion Sp. z o.o., the subject of which is the dismantling of facilities and preparation of the site at Adamów Power Plant for potential new investments.

 

Pursuant to the concluded Contract, a lump-sum remuneration in cash, in the amount of PLN 57.5 million, payable by MK Explosion Sp. z o.o. to ZE PAK SA, was established for performing the entire subject of the Contract. Settlement of the implementation of the subject of the Contract will be carried out by revenues from the sale of scrap metal, debris and other materials and equipment from dismantling. The deadline was set at 21 months from the day of handing over the dismantling area.